J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/151
The kiln wall prior to the external brickwork being laid. Initial steel wall and roof girders being erected
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/152
Kiln construction contractor George de Paoli laying bricks in the cooling zone at the exit of kiln
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/153
Steel girders in the kiln wall for supporting roof beams. External walling yet to be constructed
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/154
Kiln wall prior to external brickwork
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/155
Completed internal kiln wall at eastern end of kiln
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/156
External kiln brickwork prior to the cavity being filled with insulation
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/157
George de Paoli laying external kiln bricks. Kiln completed end of May 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/158
Northern aspect of factory showing the kiln construction, March 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/159
Unpacking of overseas machinery by employees
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/160
The company's hough pay loader of one and three-quarter cubic yard capacity
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/161
The Hyster gas operated forklift of 6,000 lbs. lifting capacity
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/162
The dryer concrete flooring prior to steel erection
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/163
Office block nearing completion, northern aspect
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/164
E.& W.S. sewerage construction on Aldenhoven Road
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/165
Aldenhoven Road sewerage installation
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/166
Permanent E.T.S.A. high voltage power installation on Aldenhoven Road
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/167
Two Alsatian security dogs owned by Southern Bricks
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/168
Alsatian security dogs used prior to the permanent security fencing around the factory
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/169
Insulated walling panels of the dryers
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/170
The Capelletti unloading machine and marshalling table
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/171
Installation of the Capelletti unloading pit and marshalling table
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/172
The three heat generators prior to being installed for generation of heat to the dryer
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/173
The E.T.S.A. sub-station with the main electrical board above
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/174
Final completion of conveyor no. 5 from the box feeders to the screen mixer and conveyor no. 6 to the high speed rollers no. 2
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/175
Conveyor no. 6 to the high speed rollers no. 2
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/176
Conveyors nos. 6 and 7 with the E.T.S.A. sub-station and main control board
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/177
High speed rollers no. 2 and electrical control boards
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/178
De-airing extrusion machine "Universal 450 Super" with sand blasting and engraving machines in foreground
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/179
Exit end of kiln
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/180
De-airing extruder showing the Capelletti column wire cutter and engraving machine