J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/121
Western end of kiln during rail track fixing
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/122
Factory construction site showing kiln ducting, pay loader. Photo taken from the office area
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/123
Completed kiln ductwork prior to installation. Dryer trolleys in background
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/124
Mixing of clay with fire cement to be used in the construction of the kiln brickwork
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/125
Drilling of the dryer foundation pier holes, March 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/126
Installation of the wet grinding pan by Robert Way Crane Services. The clay primary box feeder is shown on the left
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/127
Positioning of the wet grinding pan - total weight approx. 30 tonnes. Assembly carried out by Cooma employees
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/128
Wet grinding pan showing grinding rollers and foundation pillars
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/129
Wet grinding pan. Installed 10 April 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/130
Wet grinding pan
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/131
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/132
Unloading of high speed rollers by H. Endler
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/133
Installation of no. 1 high speed roller in the preparation area
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/134
Positioning of no. 1 high speed roller
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/135
Final fixing of no. 1 high speed roller. Installed 7 March 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/136
Installation of de-airing extrusion machine "universal 450 super" from Morando Impianti, Asti, Italy
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/137
Welding of ductwork carried out in the factory by the Cooma boilermakers
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/138
Unloading of the kiln cars manufactured by Graham Material Handlings and supplied by Colby Engineering
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/139
Unloading of kiln cars
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/140
Foundations of the office block at north east end of the factory. Foundations poured 21 February 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/141
Office block looking south
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/142
Foundations of office block
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/143
Pouring of the concrete floor slab of the office block
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/144
Unpacking of overseas machinery and construction of the office
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/145
The laying of the external brickwork of the office showing the temporary security fencing
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/146
Hough pay loader and small hyster forklift owned by Southern Bricks
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/147
Initial construction of the kiln walls using a kiln car as the template. Commencement of work 10 February 1975
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/148
Templates used in the kiln wall construction. Photograph from the eastern end
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/149
Bricklayers at work on the kiln walling
J. Hallett & Son Limited, c. 1923-1975, Photograph, BRG 215/1/150
Kiln walls nearing completion height